Holiday Happenings

I gotta say the 3-day weekends has been great and so wish we had these all the time as we got a lot done over these past couple of weekends. I hope the holiday’s were great for everyone and that you are excited for the New Year!

We got the double windows removed, the new French doors in and the water pipe capped (the water pipe came out where the new French doors are) over the Christmas holiday. This New Year’s weekend we removed the two windows and door from the west side of the room, got it all sealed back up, installed a new window and got 2 of the 3 sections of the popcorn ceiling removed. I did get a new ceiling fan ordered and 8 pendant lights which should be arriving in the next couple of weeks which will be perfect timing. It will take next weekend to get the first coat of mudding on, and finish the remainder of the popcorn ceiling removal. Then fingers crossed we will be ready the weekend after that to texture the room. We are getting there!!!

This the brace to keep the ceiling up as we took out these windows and needed to reenforce the area for the door.

Notice at the top the reinforcement, so we could remove the ceiling brace to install the doors.

Doors installed

West wall – before, we took out the windows and this door and closed it in with just a window where the door is now.

Outside looking in – this is now closed up and just a window.

Basically a completed view – just needed to do the side where the single door is (which is above where we removed it and put in a window).

Popcorn ceiling removed on 2 of 3 sections

I wanted to include this picture, this is the very top section of the ceiling that bumps up to the upstairs walkway. The builders did not texture the wall here, instead just had it popcorn textured and ran a brush over it. Needless to say, it all fell off with just touching it. Thank goodness we are doing it all over again!